What Should I Do If I Find Defects After Possession?
Document the defect immediately and notify the promoter in writing. Section 14(3) is particularly important for specified defects brought to the promoter’s notice within five years from handing over possession.
Common Problems Buyers Encounter
Depending on the facts, buyers may face seepage, leakage, structural cracks, defective workmanship, poor quality or problems with promised services. Whether a particular issue falls within Section 14(3) should be assessed from the facts and contractual obligations.
The 30-Day Rectification Requirement
For defects covered by Section 14(3), the promoter must rectify the defect without further charge within 30 days of notice. Failure to rectify within that period can lead to appropriate compensation under the Act.
Build a Defect Evidence File
Keep dated photographs, videos, written complaints, technical reports where appropriate, inspection notes, repair attempts and invoices. Avoid destroying evidence before it is documented.
When Should You Escalate?
If the promoter does not respond, refuses to rectify or disputes the defect, the buyer can evaluate the appropriate RERA complaint mechanism and other remedies available under the circumstances.
Construction Defects After Possession FAQs
Does RERA give a five-year warranty on a home?
Section 14(3) is more precise than a blanket warranty. It addresses specified structural and other defects brought to the promoter’s notice within five years from possession.
Does the builder have to fix qualifying defects free of cost?
Yes, Section 14(3) requires rectification without further charge within 30 days for defects covered by the provision.
What if the builder ignores my complaint?
Preserve the written complaint and non-response, and consider the appropriate RERA mechanism if the statutory requirements are met.
Should I get a technical inspection?
For significant structural or technical issues, an appropriately qualified inspection can help document the nature and extent of the problem.
Can I claim compensation for construction defects?
Section 14(3) provides for appropriate compensation where the promoter fails to rectify covered defects within 30 days.